Syria-Lebanon Al-Areeda Crossing to Reopen in December After Rebuild

•SP Today News Desk
Syria-Lebanon Al-Areeda Crossing to Reopen in December After Rebuild

Rehabilitation of the Al-Areeda crossing on the Syria-Lebanon border is in its final stages, with reopening expected in December 2026 after a new bridge, electronic customs and expanded facilities replace infrastructure damaged by flooding in January.

Reopening Set for December

Rehabilitation of the Al-Areeda crossing on the Syria-Lebanon border has reached its final stages, with the crossing expected to reopen in December 2026. The timing follows completion of a new bridge linking the two sides and upgrades to infrastructure, customs systems and service facilities.

Mazen Alloush, director of the international relations and cooperation department at the authority overseeing ports and customs, said the works had reached their final phases.

New Bridge and Facilities

The project rebuilds the border bridge and rehabilitates the administrative and customs building and the passenger hall. It expands yards and internal roads, creates a separate yard for freight, and upgrades water, sewage, telecommunications and solar power systems.

Coordination on the new bridge was handled with the ministry responsible for public works and housing, which oversaw the structure connecting the Syrian and Lebanese sides.

Automated Customs Planned

Once operational, the crossing is to run electronic customs clearance and deploy X-ray scanners for trucks and vehicles, with passport and immigration databases linked across systems. Separate lanes are planned for trucks and passenger cars to keep freight and travelers moving independently.

The site will also add medical and first-aid points, rest areas, free internet and closed-circuit cameras, part of an effort to modernize how the crossing handles traffic.

Closed Since January Flood

Traffic through the crossing stopped completely in early January 2026 after the Greater Southern River rose and damaged the connecting bridge. In March, the crossing reopened on foot for Syrians arriving from Lebanon, restoring limited movement while reconstruction was prepared.

Work on the new bridge resumed in May 2026 in coordination with the public works and housing ministry, paving the way for the planned full reopening.

A Route Back to Trade

A full reopening would restore a road and freight link between Syria and Lebanon that has been out of service for most of the year. Returning trucks and passenger traffic to the crossing is set to reconnect a channel for cross-border movement of goods and people along the coastal frontier.