Czech Firm to Rebuild Aleppo Units
The state-run Syrian Electricity Company signed an agreement on 15 November 2026 with Czech engineering firm Energy Care to rehabilitate three generating units at the Aleppo thermal power plant, one of the largest power stations in Syria. The signing took place at the Energy Ministry headquarters in Damascus.
The contract covers the plant's second, third and fourth units, each with a design capacity of 213 megawatts, for a combined 639 megawatts. The agreement was signed by the plant's director and the company's representative in Syria, with the energy minister and the Czech ambassador in attendance.
Staggered Repair Timeline
Work on the three units is to proceed simultaneously but finish on different dates. The third unit is scheduled to return to service 18 months after work begins, the fourth after 24 months, and the second after 30 months.
Once all three units are running alongside the first and fifth, the station's design output is expected to reach about 1,040 megawatts. The first and fifth units together account for roughly 400 megawatts of that figure.
Power for the North
The Aleppo plant is a principal source of electricity for northern Syria, where households and businesses have endured prolonged outages. Restoring 639 megawatts from the three idle units would mark one of the larger single additions to the national grid.
Earlier repairs brought the first and fifth units back into partial operation, with reported output of 195 and 202 megawatts as of May 2026. The new contract targets the remaining stalled capacity.
Financing the Deal
The agreement is valued at about $93 million (USD), according to figures given by the energy minister. Its cost and scope place it among the more substantial foreign engineering contracts awarded in the country's power sector this year.
A separate concessional loan of $90 million (USD), signed on 4 November 2026 with the Saudi Fund for Development, was earmarked for rehabilitating Aleppo's generating units. It remains unclear whether that financing covers the full value of the contract.
Foreign Engineering Returns
The deal reflects a wider push to draw outside engineering firms into rebuilding Syria's degraded power infrastructure. Reliable generation is a precondition for reviving industry and easing the cost pressures weighing on households.